RAILWAY CROSSINGS
Bronte St Watermain
Scope of work completed:
- 2no. Reception shafts of 5.5m diameter and depths of up to 10m installed in shale and clay ground conditions.
- 2no. Launch shafts of 5.5m (wide) x 6.7m (long) and depths of up to 10m installed in shale and clay ground conditions.
- Launch Shafts to facilitate the installation of the C300 Watermain and air valve/drain chambers.
- Installation of 78m of 1200mm casing pipe by Microtunnel under 16 Mile Creek.
- Installation of 60m of 1200mm casing pipe by Microtunnel under the live CP Rail tracks with just 4m of cover.
- On completion of the tunnelling works, the 400mm C300 WM with externally welded joints installed and grouted inside the tunnel casing.
- Location: Milton, Ontario
- Owner: Town of Milton
- Role: Specialist Subcontractor
- Project timeline: Sept 2021-Oct 2021, March 2022