WATERMAINS
Dixie Rd Watermain
Scope of work completed:
- 1no. Launch shaft of 7.2m diameter and depth of 13m installed in silty clay and shale ground conditions.
- 1no. Reception shaft of 5.5m diameter and depth of 13m installed in silty clay and shale ground conditions.
- Installation of 540m of 1200mm casing pipe by Microtunnel under 23 lanes of live traffic on one of North Americas busiest highways Highway 401.
- On completion of the tunnelling works, the continuously welded steel casing and C300 WM with externally welded joints installed and grouted inside the tunnel casing.
- Location: Mississauga, Ontario
- Owner: MTO
- Role: Specialist Subcontractor
- Project timeline: April 2022-Sept 2022